BRISTOL — In an effort to keep motorists informed, the Virginia Department of Transportation (VDOT) provides weekly information about highway construction and maintenance projects in southwestern Virginia. When traveling through highway work zones, use caution and be alert to changes in traffic patterns and slow-moving or stopped traffic.
To help motorists take the guesswork out of travel plans, call VDOT’s 511 or visit https://511.vdot.virginia.gov for real-time traffic information.
Entries with (NEW) or (UPDATE) indicate revisions from last week’s report.
Interstate 81 – Exit 50 and mile marker 52 bridge rehabilitations (Smyth County)
A project that includes bridge rehabilitation work on six bridges north and southbound between Exit 50 and mile marker 52 in Smyth County is underway. Be alert to construction crews in the area. Nighttime lane closures will be in place for the duration of the project. Also, be alert to flaggers and/or lane closures on Kiawana Road and Nick’s Creek Road. Pay attention to signs and message boards. (Completion: November 2027)
People are also reading…
Interstate 81 – Exit 45 deceleration lane extension (Smyth County)
A project to extend the deceleration lane at exit 45 northbound in the Marion area of Smyth County is underway. The project includes replacing the northbound I-81 bridge over Matson Drive. Be alert to periodic nighttime lane closures and shifted traffic over Matson Drive. (Completion: December 2027)
Interstate 81 – Bridge rehabilitation at mile marker 68 (Wythe County)
Due to a bridge rehabilitation project on I-81 north and southbound over Reed Creek at mile marker 68 in Wythe County, be alert to periodic extended lane closures and a width restriction of 14 feet. Pay attention to signs and message boards. (Completion: September 2027)
Interstate 81/77 interchange (Wytheville)
Due to improvements on I-81 and I-77 at the interchange at Wytheville, pay close attention to signs and message boards. Be alert to possible lane restrictions and traffic shifts. (Completion: Summer 2027)
Interstate 77/Exit 41 area (Wytheville)
Be alert to construction activities at the I-77 interchange at Exit 41, including improvements to the northbound lanes and the northbound I-77 off-ramp, Nye Road, and Peppers Ferry Road. Be alert to traffic shifts. Pay close attention to construction vehicles, work zone signs, and workers in the area. (Completion: Late 2026)
Interstate 81 – Bridge replacement at mile marker 9 northbound over Old Dominion Road (Washington County)
A bridge replacement project is underway on I-81 northbound at mile marker 9 over Old Dominion Road in Washington County. A one-lane signal is controlling traffic beneath I-81 on Old Dominion Road. (Completion: May 2027)
(UPDATE) Interstates 81 and 77 maintenance activities
Be alert to the following lane closures due to interstate maintenance activities:
Interstate 81
- Nighttime bridge inspection work north and southbound between mile markers 85 and 87 in Wythe County.
- Nighttime bridge deck repairs north and southbound between mile markers 48 and 56 in Smyth and Wythe counties.
- A super load will be traveling northbound from Bristol to the West Virginia state line the week of November 30.
- A super load will be traveling southbound from West Virginia to Bristol the week of November 30.
Interstate 77
- Nighttime tunnel maintenance southbound at the Big Walker Mountain Tunnels. All wide loads over 12 feet must stop before entering the tunnel.
Primary highways and high-traffic secondary roads
Bland County
Route 52 intersection improvements
An intersection improvement project is underway on Route 52 in Bland County at Indian Village Trail and Grapefield Road. Be alert to workers in the area. Traffic pattern changes will take place throughout the duration of the project. (Completion: August 2028)
Buchanan County
Route 460/121 Poplar Creek Phase B
Be alert to a new traffic pattern on Route 460 at Grundy due to the construction of Route 460/121 Poplar Creek Phase B. The switch is approximately 1.1 miles west of the Route 460/Route 83 (Riverside Drive/Edgewater Drive) intersection in Grundy. Motorists should be alert to flaggers in the area. (Completion: Late 2027)
Dickenson County
Route 83 roundabout at Route 637
A roundabout and a park-and-ride lot project is underway at the intersection of Route 83 and Route 637 in Dickenson County. Motorists should expect daily traffic pattern changes on weekdays for approximately two weeks. Crews are working on the southern side/Caney Ridge side of the roundabout, requiring flaggers to direct traffic and creating the possibility of multiple traffic pattern changes each weekday. Motorists are advised to pay close attention to signs and workers directing traffic through the work zone. The temporary road on Route 637 N (Rose Ridge) is closed. (Completion: Late 2026)
Smyth County
McMullin Bridge replacement on Browns Subdivision Road
A bridge replacement project is underway on Browns Subdivision Road, west of the new roundabout in Smyth County. A lane closure will be in place from 8:30 a.m. to 6 p.m. Monday through Friday. Be alert to flaggers in the area and pay attention to signs and message boards. (Completion: Fall 2027)
Route 11 roundabout at Adwolfe Road
A roundabout project located on Route 11 at Adwolfe Road in Smyth County is underway. Be alert to construction crews in the area. Temporary traffic signals are in place for traffic control. (Completion: July 2027)
Tazewell County
Route 19/460 and Route 610 intersection improvements – Claypool Hill
An intersection improvement project is underway on Route 19/460, from Adair Drive to Route 610 in the Claypool Hill area of Tazewell County. (Completion: December 2026)
Washington County
Route 19 safety improvements
Safety and traffic flow improvements are beginning on Route 19 in Washington County. Work includes the closure of Everett Hagy Road at Route 19 near Black Hollow Road and the construction of a cul-de-sac on Everett Hagy Road. Turn lane and median improvements are also included in the project. Motorists should be alert to lane shifts on Route 19 during this project. Use caution and slow down when traveling through the area. (Completion: June 2027)
Thompson Drive/Stanley Street roundabout
The roundabout project at the intersection of Thompson Drive and Stanley Street in the Abingdon area of Washington County is on hold now through the end of the school year. The project was scheduled over two construction seasons to minimize disruption to school traffic. The roadway will remain in its current configuration until the final phase of construction resumes next summer. (Completion: September 2027)
Wise County
Alternate Route 58 bridge replacement over Norfolk Southern railroad
Be alert to traffic pattern changes on Alternate Route 58 in Wise County due to replacement of the bridge over Norfolk Southern Railroad. Traffic traveling west toward Coeburn is using the eastbound lane. Traffic on Route 651 (Bull Hill Road) is not allowed to turn left on eastbound Alternate Route 58. Pay close attention to signs and message boards. (December 2028)
Wythe County
Progress Park Connector
Construction of a new 2.3-mile connector road between Nye Road and E. Lee Trinkle Road is underway, providing a direct connection to Wytheville’s Progress Park industrial site. A 0.3-mile stretch of Lover's Lane is closed and will remain closed for the duration of the project. The closed section of Lover's Lane is located 1.6 miles from Nye Road and 0.5 miles from Pepper's Ferry Road. (Completion: November 2027)
Route 671 (Crigger Road) bridge
Route 671 (Crigger Road) bridge in Wythe County has been closed due to safety concerns following an inspection. Motorists will use Route 612 (Dry Road) and Route 749 (Cedar Springs Road) to detour approximately eight miles. (Completion: March 2027)
Completed
Route 23 road improvements
Road improvements on Route 23 between the east connection of Route 23 Business and the West Connection of Route 23 Business in the Gate City area of Scott County are complete.
Route 622 (Miller Creek Road) pipe replacement
A pipe replacement project on a section of Route 622 (Miller Creek Road) approximately 1.4 miles from the Route 624 intersection in Russell County is complete.
About the district
The Bristol District encompasses more than 7,400 miles of roadway across 12 counties—Bland, Buchanan, Dickenson, Grayson, Lee, Russell, Scott, Smyth, Tazewell, Washington, Wise, and Wythe—and the cities of Bristol and Norton.