The following is a list of forecasted highway projects that may impact traffic traveling in the 12-county Salem Transportation District this week. Work schedules and construction project timelines are always subject to change and weather dependent. New information is noted by "New" and updates are noted when a current project has had an update added to the listing. The Salem District covers Bedford, Botetourt, Carroll, Craig, Floyd, Franklin, Giles, Henry, Montgomery, Patrick, Pulaski and Roanoke.
Traffic alert information
- 511: For the most current traffic and road work information, call 511, download the 511 app or visit 511 Virginia. On the 511 website, drivers can also sign up to receive personalized traffic alerts, view traffic cameras or download the free 511 mobile app for Android or iPhone.
- Facebook: Join our Salem District Facebook Page for traffic impacts and general information on projects.
- X: You can also follow us @VaDOTSalem.
People are also reading…
General road and bridge maintenance
VDOT performs the following activities as part of routine maintenance on roadways throughout the district. To submit a work order request or road repairs or assistance, contact our customer service center at 800-FOR-ROAD (800-367-7623) or submit online at my.vdot.virginia.gov.
- Paving operations: Weather permitting, crews will pave, patch and repair pavement on various routes. Lane closures may be in place, and flaggers may control traffic at times during daylight hours, 7 a.m. to 7 p.m. Drivers should watch for signs and expect possible delays.
- Surface treatment operations: Weather permitting, crews will begin surface treatment operations on various routes. Lane closures may be in place, and flaggers may control traffic at times during daylight hours. Drivers should watch for signs and expect possible delays. The road surface may be rough for several weeks after surface treatment is applied. Once it packs down, the road surface will be brushed and return to a smoother surface.
- Pavement markings: Pavement marking operations will be performed districtwide, in various counties on secondary routes. These will be mobile operations with lane closures as they proceed through each county. Motorists should use caution and follow mobile signs for direction.
- Ditching, grading, slope and shoulder repairs: Lane closures may be in place during daylight hours for shoulder repairs. Watch for flaggers controlling traffic.
- Pipe replacements: Crews will be working on various secondary roads to replace pipes under the roadway with periodic lane closures during daylight hours on weekdays. Watch for flaggers controlling traffic.
- Drainage maintenance: Crews will be working on various secondary roads where drainage issues are present with periodic lane closures during daylight hours on weekdays. Watch for flaggers controlling traffic.
- Mowing, tree trimming and brush removal (various routes): Crews will mow on secondary routes during daylight hours on weekdays. Watch for lane and shoulder closures.
- Bridge inspections: Contractors perform bridge inspections on various bridges throughout the district. Most inspections involve a bucket truck under a bridge and are performed between 8 a.m. and 3 p.m., outside of peak travel hours. Drivers may see lane or shoulder closures and flagging operations during the inspection.
- Unpaved road maintenance: Crews will be working on various secondary non-hard-surface roads, grading and replacing stone with periodic lane closures during daylight hours on weekdays. Watch for flaggers controlling traffic.
- Guardrail repairs: Lane closures may be in place for guardrail repairs at various locations. Work will be performed during daytime hours from 9 a.m. to 3:30 p.m.
Paving information
VDOT now offers coverage of tracking paving progress statewide, which allows community members and stakeholders to view specific locations slated for paving and individual details of each project. Paving season typically extends from April to November, and the map is updated weekly to detail exactly where paving projects are planned and ongoing to give residents and travelers a tool to use to plan for travel and stay safe near these work zones. Drivers can get specific information about the status of paving projects at the Virginia Roads Paving Map or www.virginiaroads.org.
Interstate 81
Interstate 81 bridge rehabilitation over Route 670 in Botetourt County
(Updated November 6, 2026) A bridge rehabilitation project is underway on I-81 at the bridge over Route 670 (Trinity Road). Drivers can expect periodic nighttime lane closures on northbound and southbound I-81. Work will also be performed under the bridge on Trinity Road, which may also require lane and road closures with flagging operations. Expected completion is summer 2027.
Interstate 81 acceleration ramp extension at exit 162 in Botetourt County
(Updated November 6, 2026) This ramp extension project will extend the on-ramp onto northbound I-81 about 1,000 feet. The project also includes installing drainage structures and constructing a retaining wall alongside the slope. As work progresses, additional ramp and lane closures may be in place during nighttime hours. During construction, barrier wall will be installed along the right shoulder of northbound I-81 and the on-ramp at exit 162. Electronic message boards will alert drivers to any updates or changes. Work is expected to be completed in late 2026.
- Lane closures:
- Weather permitting, alternating northbound and southbound lane closures for drainage improvements may be in place on Route 11 in Buchanan between I-81 and the Exxon station next to the northbound off-ramp at exit 162. All I-81 ramps will remain open.
- Drivers can expect other nighttime right and left lane closures in place on I-81. Drivers should use caution in the area of the work zone.
Interstate 81 bridge work at exit 94 over Route 99 in Pulaski County
(Updated October 30, 2026) A project to repair structural steel beams on the I-81 bridge over Route 99 is underway. Lane closures during daytime hours of 7 a.m. to 4 p.m. are in place on Route 99, Monday through Friday. Expected completion is November 2026.
Interstate 81 bridge work at exit 156 in Botetourt County
(Updated November 6, 2026) Bridge work is underway on northbound and southbound I-81 at exit 156. Milling and paving the bridge deck will take place in both directions, beginning with the northbound side first and then southbound once northbound is completed. Drivers can expect lane closures on I-81 during nighttime hours. Slow-roll operations are expected periodically, and flagging operations will be used during barrier wall placement on Route 640 (Brughs Mill Road). Expected completion is fall 2026.
- Slow rolls: Slow-roll operations are possible during nighttime hours, 12 a.m. to 5 a.m., on I-81 for bridge jacking and blocking. Slow-roll operations for northbound will start at exit 150 and slow-roll operations for southbound will start at the Troutville Rest Area at mile marker 158.
- Flagging operations: Flagging operations will be in place on Route 640 under the bridges at exit 156.
- Barrier walls: Temporary traffic barrier is in place on the westbound side of Route 640 under the I-81 bridges off exit 156, with lanes narrowed to 11 feet.
- Nighttime lane closures: Nighttime outside and inside lane closures may be in place on I-81 from mile marker 155 to 157, 9 p.m. to 6 a.m. the following morning.
Interstate 81 lane widening construction project exit 137 to exit 141
(Updated November 6, 2026) All three lanes through this section are now open to traffic in both directions. This $179 million design-build project to widen both directions of I-81 between mile markers 136.6 and 141.8 from two to three lanes is nearing completion. Work is being performed along a five-mile section of both northbound and southbound Interstate 81 in Roanoke County and the city of Salem. Barrier wall may be in place along the shoulders. Periodic lane closures are scheduled during nighttime hours or outside of peak travel times on northbound and southbound I-81 as needed as the project progresses in its final stages of construction. Expected completion is in fall 2026.
- Ramp closures: Drivers may see ramp closures for the paving of exit 137 and 140 on- and off-ramps from and onto northbound and southbound I-81 in Salem, 10 p.m. to 5 a.m. Watch message boards for updates on times and dates of occurrence and plan ahead.
- Milling and paving: Paving operations will require lane closures northbound and southbound during nighttime hours, 9 p.m. to 5 a.m. the following morning.
- Lane closures: Alternating left and right lane and shoulder closures during nighttime hours between 8 p.m. and 6 a.m., Sunday through Thursday, are possible. Lane widths will be reduced to 11 feet. Nightly lane closures may be in place along the right lane with possible nightly ramp narrows as needed for guardrail and shoulder strengthening.
- Work zone speed: Drivers should adhere to posted 60 mph speed limits in the work zone and allow space when following a vehicle. Narrow spacing in lanes due to barrier walls, lack of shoulders and lane shifts in various locations are present.
I-81 widening from mile marker 143 to 150
(Updated November 6, 2026) The I-81 widening project is underway. Northbound and southbound lane closures are possible during nighttime hours. Various tasks are being performed throughout the project. The expected completion for this project is summer 2031.
- Park and ride spaces blocked: The front corner area parking spaces (first two or three spaces) may be blocked off 24 hours a day during the week for signal installation work.
- Ramp closures and narrowing ramps: Various closures and narrowing of ramps will be in place over the next few weeks. Drivers may need to use alternate exits and watch message boards for the most updated information.
- Truck entrances on I-81: Openings for trucks to enter into the work zone for deliveries are possible where barrier walls and signage indicating construction entrance only are present. Watch for trucks that may slow down on the interstate to enter these areas.
- Barrier walls: Drivers will continue to see barrier walls with an eight-foot shoulder being put into place throughout the project. Drivers should watch for changes in traffic patterns.
- Traffic shift: Southbound traffic is shifted to the right shoulder from exit 150 in Botetourt County to exit 146 in Roanoke County.
- Lane closures: Periodic right and left lane closures with shoulder closures are in place during nighttime hours, 9 p.m. to 6 a.m., on northbound and southbound I-81.
- Flagging operations: Flagging operations are possible on various secondary roads impacted by bridge work. Watch for message boards and signage.
- Daytime flagging operation on Reservoir Road.
- Daytime flagging operation on Belle Haven Road.
- Ramps: Ramps on I-81, northbound and southbound, may experience periodic closures or be narrowed at exit 150, exit 146 and exit 143.
- Shoulder closures: Shoulder closures are in place with additional barrier wall to be installed next year.
- Work zone speed: Drivers should adhere to posted 60 mph speed limits in the work zone and allow space when following a vehicle. Speed reminders are posted for drivers.
- Pink detour signs: While pink detour signs are in place on I-81 and routes around the project such as Route 11 and Plantation Road, these do not designate a permanent or scheduled detour. The signed detour route is suitable for all traffic during incidents including tractor-trailers and other large vehicles. These signs are used for traffic incident detours only.
I-81 Ironto Segment N widening from mile marker 133.8 to exit 137
(Updated October 2, 2026) The I-81 widening project from mile marker 133.8 to exit 137 will begin with work to collect survey and geotechnical data that may require periodic northbound and southbound right and left lane and shoulder closures during nighttime hours. This is the northern portion of a larger project that extends to mile marker 127 at Ironto. It is being performed in three sections with this being the first section and is expected to start in early 2027.
I-81 northbound at exit 105 New River Bridge replacement in Montgomery County
(Updated October 23, 2026) Work on this project continues with the initial work beginning behind the barrier wall. Then, beginning in May and through September, the barrier wall will be moved and the existing lanes will be narrowed. In the fall of 2026, I-81 traffic will be shifted into a new pattern at the bridge. Two lanes of traffic will continue to be open in the work zone, but motorists will be traveling on a different portion of roadway on the right side of the bridge.
Throughout construction, two lanes of northbound I-81 will remain open during daytime hours with nighttime closures possible during the hours of 8 p.m. to 6 a.m. Slow rolls may be performed on I-81 in the northbound and southbound lanes from mile marker 98 to 109. Speed limit is reduced to 60 miles per hour in the work zone. The project is expected to be complete and the bridge in its final configuration with two lanes of Interstate 81 and the right deceleration lane and exit ramp by summer 2027.
- Lane closures: Nighttime right and left lane closures may be in place on I-81 northbound or southbound between mile marker 98 and 109 from 8 p.m. to 6 a.m. the following morning.
- Slow rolls: Slow rolls may be utilized periodically on both the northbound and southbound lanes from mile marker 98 to 109 for structural steel deliveries and setting beams.
- Speed limit: The speed limit is reduced to 60 miles per hour in the work zone.
I-81 bridge deck repairs
(Updated November 6, 2026) Weather permitting, crews will repair bridge decks on Interstate 81 between mile markers 170 to 89. Right and left lane closures will be in place northbound and southbound during nighttime hours, 9 p.m. to 6 a.m. the following morning. Drivers should watch for signs and work zone areas. Delays are possible.
I-81 patching operations
(Updated November 6, 2026) Weather permitting, crews will perform paving and patching operations. Lane closures as well as ramp closures may be in place northbound and southbound, Sunday through Friday, during nighttime hours, 9 p.m. to 6 a.m. the following morning. Drivers should watch message boards and signs for the latest information. Delays are possible.
Interstate 581
I-581 bridge work at exit 3E (Hershberger Road)
(Updated October 16, 2026) Weather permitting, closures may be in place during nighttime hours from 9 p.m. to 6 a.m. through mid-November. The I-581 southbound on-ramp and off-ramp at exit 3E (Hershberger Road) may be closed for bridge repairs. The northbound ramps will not be affected. Drivers should watch message boards for the most updated information.
Interstate 581 exit 2N at Peters Creek Road
(Updated October 23, 2026) The new signal has been activated but work will continue on this $4 million project to realign and signalize the exit 2N ramp from northbound I-581 to northbound Peters Creek Road. Remaining work includes grading and widening of the new ramp and demolition of the old ramp, which should be completed by the end of 2026.
- Ramp closures: Ramp closures are possible for work on the ramp. Message boards will update drivers.
- Lane closures: Drivers may still see intermittent lane closures in place, 9 a.m. to 2 p.m., on Peters Creek Road northbound and southbound in the city of Roanoke between Valleypointe Parkway and Thirlane Road NW as work continues.
I-581 patching operations
(Updated November 6, 2026) Weather permitting, crews will perform paving and patching operations. Lane closures as well as ramp closures may be in place northbound and southbound, Sunday through Friday, during nighttime hours, 9 p.m. to 6 a.m. the following morning. Drivers should watch message boards and signs for the latest information. Delays are possible.
I-581 bridge deck repairs
(Updated November 6, 2026) Weather permitting, crews will repair bridge decks on Interstate 581. Right and left lane closures may be in place during nighttime hours, 9 p.m. to 6 a.m. the following morning. Drivers should watch for signs and work zone areas. Delays are possible.
Interstate 77 (Carroll County)
I-77 mowing operations
(Updated October 23, 2026) Weather permitting, crews will be performing mowing operations on Interstate 77. Drivers may encounter lane closures Monday through Saturday during nighttime hours, 9 p.m. to 6 a.m. Shoulder closures are also possible during daytime hours. Drivers should watch for signs and slow-moving equipment.
I-77 culvert rehabilitation project
(Updated November 6, 2026) A culvert rehabilitation project is underway in two different locations under I-77. Flagging operations and temporary lane and shoulder closures will be in place. Expected completion is by the end of 2026.
- Culvert location 1: Under I-77 at mile marker 23.6 on Route 743 (Pleasant View Road). Intermittent flagging between the hours of 7 a.m. to 5 p.m. on Route 743 (Pleasant View Road) may be in place. There are no traffic impacts to I-77 at this location.
- Culvert location 2: At mile marker 8 on I-77, a second culvert project is underway. There will be some impacts to the ramp shoulder on exit 8 and a lane closure may be in place on Route 148 (Chances Creek Road) for several days.
I-77 paving and patching operations
(Updated November 6, 2026) Weather permitting, crews will perform paving and patching operations on Interstate 77. Right, left and center lane closures may be in place northbound and southbound, Monday through Friday, during nighttime hours, 9 p.m. to 6 a.m. the following morning. Paving of ramps may also occur and drivers should watch for signs and expect possible delays.
I-77 bridge deck repairs
(Updated November 6, 2026) Weather permitting, crews may perform paving operations on Interstate 77. Right and left lane closures will be in place northbound and southbound during nighttime hours, 7 p.m. to 6 a.m. the following morning. Drivers should watch for signs and expect possible delays.
Roanoke City
None to report.
Roanoke County
Dry Hollow Road safety improvements
(Updated November 6, 2026) A safety improvement project on Dry Hollow Road that will reinforce the retaining wall and install a roadside barrier is ongoing. Drivers will encounter flagging operations and delays between 7 a.m. to 4 p.m., Monday through Friday. Overnight closures on weekends and during Roanoke County schools' winter and spring breaks are possible. VDOT will provide advance notice of any additional overnight closures as needed. Temporary parking sites will be in place on either side of the roadway. Drivers should pay attention to message boards that are already in place. A new signal has already been installed as the first part of this project. Expected completion is fall 2027.
- Starting Monday, November 9, Dry Hollow Road at West River Road will be closed overnight from 11 p.m. to 5 a.m. for approximately four days. The road is scheduled to reopen every morning by 5 a.m. and the work to install a pipe is expected to be completed by the morning of Friday, November 13.
Apperson and Orchard Drive safety improvement
(Updated October 23, 2026) The installation of a new traffic signal and new turn lanes has been underway as part of safety improvements at the intersection of Apperson Drive and Orchard Drive in Salem. Paving and marking work has been completed. Lane closures are still possible. Electronic message boards and signs will alert drivers with updates. Estimated completion is late fall 2026.
Route 221 (Bent Mountain Road) utility work
(Updated October 30, 2026) Drivers should expect daytime flagging along Route 221 (Bent Mountain Road) between Poage Valley Road and Crystal Creek Drive for utility installation through November 2026. Delays are possible.
Route 220/Route 419 diverging diamond interchange
(Updated October 16, 2026) The Route 220/Route 419 interchange project is underway. It will be reconfigured with a diverging diamond concept and multiple intersections on both Route 220 and Route 419 will be modified to enhance signal timing and reduce congestion. The intersections that include Route 220 are at Valley Avenue/Southern Hills Drive, Crossbow Circle/Pheasant Ridge Road, Buck Mountain Road/Stable Road and Indian Grave Road/Clearbrook Village Lane. The intersections on Route 419 are at Ogden Road, Elm View Road and South Peak Boulevard. With multiple activities scheduled, completion at different locations will take place throughout the life of the project. Daytime, 9 a.m. to 3 p.m., and nighttime, 7 p.m. to 6 a.m., work hours will occur depending on location. Drivers should expect alternating lane closures, turn lane closures and shoulder closures. Expected completion is fall 2028.
Route 220 at Crossbow Circle and Pheasant Ridge Road intersection improvements
(Updated October 16, 2026) Construction activities for this project are underway. A new traffic pattern will be put in place where drivers will turn left or right to make a U-turn instead of driving straight across Route 220. Signal pole installation and pedestrian improvements remain under construction during nighttime hours. Drivers should use caution in the area and watch for work zones and message boards providing updated information. Expected completion, weather permitting, is by end of 2026.
Route 220 at Southern Hills and Valley Avenue intersection improvements
(Updated October 9, 2026) Drivers are now using a new traffic pattern at the intersection of Southern Hills and Valley Avenue on Route 220 that was recently completed to improve safety and traffic flow. Motorists who used to drive straight across Route 220 at this intersection will instead turn right or left onto Route 220 and make a U-turn at the next available median crossover or signal. Signal installation and pedestrian improvements remain under construction during nighttime hours. Drivers should watch message boards. Expected completion, weather permitting, is by end of 2026.
- Lane closures: Nighttime right lane closures on Route 220 northbound and southbound at the intersection of Southern Hills and Valley Avenue are scheduled for Tuesday.
Bedford County
Route 460 intersection improvements
(Updated August 28, 2026) Intersection improvements on Route 460 are underway in the vicinity of Route 668 (Blackwater Road). A new traffic pattern is in place with a left lane closure and barrier wall on eastbound Route 460 and a left shoulder closure with barrier wall on westbound Route 460. This pattern will continue through the duration of the project. Message boards are posted. Expected completion is November 2026.
Botetourt County
Route 460 and Laymantown Road intersection improvements
(Updated September 11, 2026) An intersection improvement project to replace a bridge and add a right-turn lane on westbound Route 460 for drivers turning onto Laymantown Road is nearing completion. Laymantown Road is open to traffic. The project still has work that will continue, including milling and paving, markings, signal work and other residual needs in the area, but traffic will be able to use the roadway during remaining construction. Drivers should pay attention to signs and traffic control devices and use caution in the work zone.
- Lane closures: Drivers who use Route 460 (Orange Avenue) and Route 658 (Laymantown Road) in Botetourt County should expect possible lane closures on Route 460 from 7 p.m. to 6 a.m. and on Laymantown Road from 8:30 a.m. to 2 p.m. and 3:30 p.m. to 7 a.m.
Craig Botetourt Scenic Trail stabilization work
(Updated November 6, 2026) Residents along the former Chesapeake and Ohio (C&O) Craig Valley Branch railbed in Botetourt and Craig counties may notice maintenance work continuing along the old railbed. These activities are intended to prevent additional deterioration and to help designers who are developing plans for the Craig Botetourt Scenic Trail. VDOT continues to conduct site visits and field reviews on the railbed. The design plans for Craig Botetourt Scenic Trail are still being refined. The project is set to begin by the end of 2026 with a completion date of fall 2028.
Carroll County
Route 743 and Route 148 impacted for I-77 culvert rehabilitation project
(Updated November 6, 2026) A culvert rehabilitation project is underway in two different locations under I-77. Flagging operations and temporary lane and shoulder closures will be in place. Expected completion is by the end of 2026.
- Culvert location 1: Under I-77 at mile marker 23.6 on Route 743 (Pleasant View Road). Intermittent flagging between the hours of 7 a.m. to 5 p.m. on Route 743 (Pleasant View Road) may be in place. There are no traffic impacts to I-77 at this location.
- Culvert location 2: Work is underway at mile marker 8 on I-77. There will be some impacts to the ramp shoulder on exit 8 and a lane closure may be in place on Route 148 (Chances Creek Road) for several days.
Craig County
Craig Botetourt Scenic Trail brush cutting and stabilization work
(Updated November 6, 2026) Residents along the former Chesapeake and Ohio (C&O) Craig Valley Branch railbed in Botetourt and Craig counties may notice maintenance work continuing along the old railbed. These activities are intended to prevent additional deterioration and to help designers who are developing plans for the Craig Botetourt Scenic Trail. VDOT continues to conduct site visits and field reviews on the railbed. The design plans for Craig Botetourt Scenic Trail are still being refined. The project is set to begin by the end of 2026 with a completion date of fall 2028.
Floyd County
None to report.
Franklin County
Route 220 intersection improvements at Bonbrook Mill Road
(Updated October 16, 2026) A project to improve safety by converting the crossover at the intersection of Route 220 (Virgil H Goode Highway) and Route 635 (Bonbrook Mill Road) to an unsignalized Continuous Green-T is underway. The Bonbrook Mill Road crossover has been closed and a signed detour is in place for drivers who typically turn left from Bonbrook Mill Road onto Route 220 southbound. Southbound Route 220 drivers who typically turn left onto Bonbrook Mill Road will also have a detour. These detours will be in place through the duration of the project. In addition, lane closures and flagging operations are possible between the hours of 7 p.m. and 6 a.m. and 9 a.m. to 3 p.m. Drivers should pay attention to signs and message boards. Work is expected to be completed by the end of 2026, weather permitting.
Route 728 (Leaning Oak Road) pipe replacement
(New October 23, 2026) Effective Monday, November 9, a section of Route 728 (Leaning Oak Road) will be closed for a pipe replacement project. The structure is located 0.48 mile south of Route 739 (Bethlehem Road) and 1.05 miles north of Route 693 (Green Level Road). Work is scheduled for completion by Friday, November 20, 2026.
Route 220 at Grassy Hill safety improvements
(New October 16, 2026) Work to make road improvements and an acceleration lane onto Grassy Hill Road from 0.284 mile north of Grassy Hill Road to 0.069 mile south is underway. Flagging operations will be in place as needed during construction. Work is expected to be completed in late fall 2027.
Route 220 and Route 613 (Naff Road) safety improvements
(Updated October 16, 2026) This project is currently underway and will construct a new southbound right-turn lane on Route 220 before Route 613 (Naff Road) and extend the existing northbound left-turn lane on Route 220. Drivers can expect flagging operations as needed during construction. Expected completion is fall 2027.
Giles County
None to report.
Henry County
Route 220 and Dyer Street intersection improvements
(Updated October 9, 2026) Intersection improvements continue at Route 220 and Dyer Street. A new traffic pattern is now in place where drivers will turn left or right to make a U-turn instead of driving straight across Route 220. Daytime and nighttime lane and shoulder closures are possible, as well as alternating lane and turn lane closures in the area. Motorists should watch message boards for traffic pattern shifts and closures. Expected completion is by end of 2026.
Montgomery County
Route 114 (Peppers Ferry Road) and Prices Fork Road intersection improvements
(Updated October 23, 2026) Work is underway at the intersection of Route 685 (Prices Fork Road) and Route 114 (Peppers Ferry Road). This intersection improvement project includes adding a new right-turn lane for drivers going west on Peppers Ferry Road to turn onto northbound Prices Fork Road, adding a new right-turn lane for drivers going south on Prices Fork Road to turn onto westbound Peppers Ferry Road and widening the Peppers Ferry Road eastbound shoulder south of the intersection. In addition, the $8.3 million project will add pedestrian accommodations, drainage improvements and replace the existing signal at the intersection. The intersection will remain open at all times, but lane closures and flagging operations are possible between the hours of 9 a.m. and 3 p.m. and 6 p.m. to 7 a.m. as needed. Drivers should pay attention to signs and message boards in the area. Work is expected to be completed in late 2027.
Route 460 eastbound slope repairs scheduled in Christiansburg
(New October 23, 2026) Beginning Monday night, October 26 at 7 p.m., concrete barrier wall with a right lane closure will be installed to perform slope repairs on Route 460 eastbound between exit 3A and exit 2. During nighttime hours, Sunday night through Friday morning, 7 p.m. to 6 a.m., a right lane closure will be in place. During daytime hours, a continuous shoulder closure will remain in place. Drivers may experience delays or choose to seek alternate routes. Work is expected to be completed in the next two to three weeks.
Route 8 widening and pedestrian improvements
(New October 30, 2026) A project on Route 8 in the town of Riner between the Riner Post Office and Auburn Middle School is underway. The project will widen Route 8 and expand the middle turn lane starting at the intersection with Route 669 (Union Valley Road) and run approximately 0.27 mile south of the intersection. It will also add curb and gutter and sidewalks as well as drainage improvements. Drivers should use caution in the area. Expected completion is summer 2028.
- Lane closures with flagging: Route 8 will be reduced to one lane maintained by flagging operations as needed between the hours of 10 p.m. and 7 a.m. the following morning.
- Detour: Intermittent nighttime detour may be in place using Route 671 (Five Points Road) between the hours of 10 p.m. and 7 a.m. the following morning.
Patrick County
Route 672 (The Hollow Road) emergency roadwork
(Updated October 16, 2026) A section of Route 672 (The Hollow Road) is closed to through traffic for emergency repairs after recent flooding damaged the bridge over Ararat River near Route 773 (Ararat Highway). Drivers will need to use alternate routes. The bridge is still being assessed and engineering is ongoing. Work will begin after water recedes and materials arrive, weather permitting. There is no anticipated reopening date at this time.
Intersection improvements at Route 8 and Route 836
(Updated November 6, 2026) A project to improve the intersection at Route 8 and Route 836 (Ashby Drive) is underway. This project will replace drainage structures and install a left-turn lane from Route 8 northbound onto Route 836 (Ashby Drive) westbound. Drivers can expect periodic traffic pattern changes and flaggers to control alternating traffic on Route 8 and Route 836 (Ashby Drive). The one-lane road flagging operation with rumble strips on Route 8 southbound will be in place intermittently for the duration of the project. The speed limit will be reduced to 25 mph in the work zone. While school is in session, flagging operations will be limited to the hours between 9 a.m. and 2:30 p.m. Drivers may experience delays or seek alternate routes. Motorists should pay attention to signs and electronic message boards that will be posted to alert drivers to the changes. The project is scheduled to be completed by the end of 2026.
- Blasting operations: On Wednesday, November 11, blasting has been scheduled between the hours of 9 a.m. and 2 p.m. Traffic will be controlled by a flagging operation for a full stop up to 15 minutes in duration on Route 8, Ashby Drive and Wayside Drive. A second blast will be scheduled at a future date and time. Drivers should watch message boards for notification.
- Traffic pattern change: Drivers can expect a new traffic pattern on Route 836 (Ashby Drive) that diverts traffic onto a gravel surface while a pipe replacement is completed. This traffic shift is expected to be in place for approximately three months.
Route 58 Lover’s Leap project
(Updated November 6, 2026) Construction is nearing completion on the Lover’s Leap area of Route 58. Message boards are in place to alert traffic of activities. Estimated completion date is late fall 2026.
- Eastbound lanes, truck ramps and the new overlook are now open.
- Drivers can expect periodic lane closures and flagging operations for residual work as the project progresses to its final completion.
Route 58 Vesta project
(Updated October 30, 2026) Construction activities on the Route 58 Vesta project are expected to begin the week of November 2. The project is located near the Route 58 Business eastern intersection in Meadows of Dan and ends about 0.5 mile east of Route 610 (Cloudbreak Road). In addition to widening Route 58 from two lanes to four lanes, the project includes replacing the existing bridge over the Dan River with two new bridges. The Vesta project adjoins the Lovers Leap widening project that has been under construction. Once construction begins, motorists can expect flagging operations and temporary traffic pattern changes. A temporary signal will become active in spring 2027. Message boards will alert drivers. Traffic is expected to be in its final configuration in fall 2030 with final completion of the project in summer 2031.
- Flagging operations: Beginning November 4, clearing and grubbing activities will be performed with flagging operations in place. Drivers should watch for message boards and use caution in work zones.
Pulaski County
Route 11 turn lane improvements at Fairlawn Plaza
(New October 30, 2026) Beginning mid-November 2026, work will begin on Route 11 to expand the turning lane from Route 11 northbound on Fairlawn Plaza as well as sidewalk additions and drainage improvements. Lane closures on Route 11 southbound and northbound will be in place, but most of them will be in the northbound direction. During the day until May 31, 2027, lane closures will only be allowed between 9 a.m. and 2 p.m. and after 7 p.m. in the evening. After May 31, 2027, and during the summer months, these restrictions may be lifted. Lane closures will always be at least 11 feet in width. Expected completion is late fall 2027.
Roundabout construction at Cougar Trail Road and Newbern Heights Drive
(Updated October 23, 2026) Construction is underway on a single-lane roundabout at the junction of Route 611 (Newbern Road), Route 643 (Cougar Trail Road) and Route 1120 (Newbern Heights Drive). This project also involves realigning all three roads and will include reinforced concrete around the island to enable larger vehicles to navigate the turns.
- Detour: Residents who live on Route 1120 (Newbern Heights Drive) will need to use the second entrance located about 0.5 mile south on Route 611 (Newbern Road). Message boards are in place alerting the public. The first entrance near Route 643 (Cougar Trail Road) will be closed for the duration of the project.
During daytime hours between 9 a.m. and 2 p.m. and evening hours between 6 p.m. and 7 a.m. the following morning, Monday through Friday, flaggers may control traffic with traffic reduced to one lane. Delays are possible. Flagging operations will not be in place during peak hours between 7 a.m. and 9 a.m. and 2 p.m. and 6 p.m., Monday through Friday. In addition, drivers should also be alert to traffic shifts and changing traffic patterns while the roundabout is under construction. Message boards will alert drivers. The new roundabout is expected to be open to traffic in spring 2028. Once the roundabout is open, residual work in the area will be performed.
Route 11 safety improvements at Warden Court
(Updated October 30, 2026) Work is nearing completion to improve roadway elevation through the curve on Route 11 at Warden Court between the intersections of Route 11 and Camelot Farm Road and the northern entrance to Warden Court. Drivers can expect southbound lane and shoulder closures with barrier wall and alternating northbound and southbound lane closures. Eleven-foot lanes will be maintained in both directions. Expected completion is November 2026.
Route 11 at Route 114 (Peppers Ferry Road) intersection safety improvements
(Updated October 30, 2026) Drivers can expect lane, turn lane and shoulder closures with periodic detours and flagging operations for a safety improvements project that is underway at the intersection of Route 11 (Lee Highway) and Route 114 (Peppers Ferry Road). Periodic temporary detours will be in place using Route 600 (Belspring Road) for traffic exiting southbound Route 11 to eastbound Route 114 and using Route 630 (Round House Street) for traffic exiting westbound Route 114 to southbound Route 11 as work progresses. A nighttime detour may be in place with traffic using Round House Street to access Route 11 southbound. Daytime lane closures are currently limited to the hours between 9 a.m. and 2 p.m., and overnight between 7 p.m. and 6 a.m. through the end of November. Motorists should pay attention to electronic message boards in the area for changes in traffic patterns and periodic detours. Expected completion of this project is summer 2027.